Pavement Stabilisation & Flood Repairs | Gympie Regional Council DFRA Package 1

Projects

Project Name:
Gympie Regional Council DFRA Package 1

Location: Gympie Regional Council District

Client: Gympie Regional Council

Value: $10 Million

Start/Finish Date: May 2023 – December 2023

Description:
Insitu Stabilisation of Sealed Pavements caused by Flooding 2021/22.

Scope:

  • Traffic Management

  • Side track construction

  • Excavation

  • Subgrade treatment

  • Concrete floodway construction

  • Signage installation

  • Insitu cement stabilisation

  • Pavement sealing and linemarking

  • Additional 35,000 m² of sealed pavement stabilisation

  • Repairs/replacement to drainage structures and landslips


Challenges
:

  • Spread over a vast area of the GRC

  • Successful delivery of additional scope, ahead of schedule (5 months)

  • Complex logistics due to terrain and conditions