Design & Construct Pavement Rehabilitation and Asphalt Works

Projects

Location: Minden

Value: $2,100,000

Client: Somerset Regional Council

Duration: March 2024 – May 2024

 

Description: The project involved upgrading the heavily trafficked intersection of Lowood Minden Road, Zabels Road, and Oscar Road to improve safety, traffic flow, and accessibility. Brown Contractors implemented a phased approach to minimize disruptions, effectively accommodating an AADT volume of 6,100 vehicles per day.

Scope:

  • Excavation of 2,000m³ of material for disposal.

  • Importing and placement of quarry gravel.

  • Laying 680 tonnes of asphalt to enhance durability.

  • Application of sealing and line marking.

  • Installation of road furniture.

Challenges:

  • Poor subgrade conditions required careful management.

  • Utility service conflicts addressed successfully.

  • Maintaining continuous traffic flow through phased construction, temporary lane diversions, and comprehensive traffic control measures.

 